On this page
- Can I get government help to pay for rural broadband?
- Which schemes are open, closed or changing?
- What is Project Gigabit, and is my home included?
- What happened to the Gigabit Broadband Voucher Scheme?
- What is the broadband Universal Service Obligation, and how do I use it?
- What help is there in Scotland?
- What help is there in Wales?
- What help is there in Northern Ireland?
- Does my council offer anything?
- What are my rights if my current broadband is slow or keeps failing?
- What if no scheme covers my home?
- What to do next
- Frequently asked questions
- Sources
Direct grants for rural households have mostly closed. The UK Gigabit Broadband Voucher Scheme stopped taking new projects on 31 August 2026, Scotland's voucher scheme closes to new applications on 20 November 2026, and the Welsh grant has not been accepting applications since May. What remains is large public funding paid to network builders, which helps you only if your home is in a build area, and one legal right that applies everywhere in the UK: the right to request a connection of at least 10 Mbps, with BT paying up to £3,400 of the cost.
Key takeaways
- Do not plan around a voucher unless you are already in a registered project. New voucher projects are closed in England, Wales and Northern Ireland, and close in Scotland on 20 November 2026.
- Most public money now goes to builders, not households. Check whether your address is inside a Project Gigabit, R100 or Welsh or Northern Irish contract area. If it is, you wait; you do not apply.
- You have a legal right to request decent broadband. It is called the Universal Service Obligation. The cost cap is £3,400 and the price test is £59.60 a month.
- Cheaper satellite has narrowed that right. If an affordable satellite or mobile service can give you 10 Mbps, you probably will not qualify for a line.
- You also have rights against your current provider. Automatic compensation for slow repairs and missed appointments, and an independent complaints scheme after six weeks.
- A small number of homes are officially "Very Hard to Reach". For those, the realistic answer is wireless or satellite.
Can I get government help to pay for rural broadband?
Possibly, but probably not in the form of a cheque or voucher.
It helps to separate three kinds of help:
- Supply-side funding. Government pays a network builder to extend full fibre into areas that would not pay for themselves. You do nothing except order a service when it arrives. This is where nearly all the money is: Project Gigabit across the UK, R100 in Scotland, and separate contracts in Wales and Northern Ireland.
- Vouchers and grants. Government pays part of the cost of connecting a specific group of homes, or one home. These are the schemes that have closed or are closing.
- Legal rights. Rules that oblige a company to do something for you: build a connection, pay compensation, or let you leave a contract.
Nothing from government pays your monthly bill. Most large providers do offer cheaper social tariffs to people on certain benefits, such as Universal Credit, and Ofcom keeps a list (House of Commons Library).
Which schemes are open, closed or changing?
Every row was checked on 13 November 2026 against the source linked.
| Scheme | Where | What it does | Status | Source |
|---|---|---|---|---|
| Project Gigabit contracts | UK-wide | Pays builders to bring gigabit-capable broadband to areas with no commercial plan | Open and building. Target: 99% of premises by 2032. Further contract awards planned to the end of 2027 | GOV.UK |
| Gigabit Broadband Voucher Scheme | UK-wide | Up to £4,500 per premises towards a group project | Closed to new projects since 31 August 2026. Existing projects continue; scheme ends 31 March 2028 | GOV.UK |
| Broadband Universal Service Obligation | UK-wide | Legal right to request at least 10 Mbps download and 1 Mbps upload; BT pays up to £3,400 | Open. Government has said it will review it "in due course" | BT, Commons Library |
| R100 contracts | Scotland | Scottish Government contracts with Openreach for full fibre in the North, Central and South areas | Building. Contract build expected to finish in 2028 | Scottish Government |
| Scottish Broadband Voucher Scheme | Scotland | Up to £5,000 for premises with no superfast broadband planned | Closes to new applications on 20 November 2026 | Scottish Government |
| Access Broadband Cymru | Wales | Grant towards installing an alternative connection | Application window closed since 1 May 2026, pending review. No change found | Welsh Government |
| Extending High Speed Broadband | Wales | £70 million of Welsh Government contracts for premises nobody else will reach | In procurement and delivery | Welsh Government |
| Project Gigabit Northern Ireland | Northern Ireland | £34.6 million contract with Fibrus for more than 9,000 rural premises | Building. Due by the end of 2027 | Department for the Economy |
What is Project Gigabit, and is my home included?
Project Gigabit is the UK Government's programme to get gigabit-capable broadband, meaning a connection able to deliver 1,000 Mbps, to premises that commercial builders would leave out. In nearly every case that means FTTP (fibre to the premises, or full fibre): a fibre-optic cable all the way into the building.
The facts as of the government's September 2026 update (GOV.UK):
- The target is gigabit-capable coverage for 99% of UK homes and businesses by 2032.
- Coverage stood at more than 88% in January 2026, leaving about 4 million premises without it. The government notes that these are increasingly in towns and cities as well as the countryside.
- More than £2 billion has been committed through signed contracts.
- The delivery body, Building Digital UK, reviews operators' plans every four months and intends to finish awarding contracts under its cross-regional framework by the end of 2027.
- Building Digital UK transferred to the Department for Digital, Culture, Media and Sport in July 2026, according to the update.
How to check. Use the GOV.UK gigabit availability checker (GOV.UK). It reports one of three things for your address: gigabit-capable broadband is available, it is planned, or it is not in any known plans. If you are in a Project Gigabit contract area, it tells you. The other checkers worth running are listed in the complete rural broadband guide.
What "planned" is worth. Less than a promise. Trade press analysis of Building Digital UK's figures showed about 250,000 premises built out of roughly 1.05 million contracted by April 2026 (ISPreview). Contracts change. One covering parts of the Peak District ended by mutual agreement in 2025, and the premises were put into a different contract within a year (GOV.UK). In 2026 trade press also reported builders scaling back in some areas, with other operators expected to pick up the work (ISPreview).
So if the checker says "planned", find out who the contractor is, look at their published timetable for your area, and ask your council's broadband or digital team what they have been told. Do not sign a long contract for an expensive alternative until you have a date you believe.
If you are in the last 1%. The government says plainly that a small number of premises will be exceptionally difficult or too costly to connect. They are classed as Very Hard to Reach, sit outside Project Gigabit, and are expected to rely on fixed wireless and satellite, which the government says it is monitoring and supporting (GOV.UK). If that is you, the practical guides are 4G and 5G home broadband in the countryside and Satellite broadband for rural UK homes.
What happened to the Gigabit Broadband Voucher Scheme?
The voucher scheme let groups of rural homes and small businesses pool vouchers worth up to £4,500 each towards the cost of a full fibre build, arranged through a registered supplier. It could only be used where there was no Project Gigabit contract and no commercial plan (GOV.UK).
The wind-down dates are:
- 31 August 2026. Last day for suppliers to submit new voucher projects. This has passed.
- 31 March 2027. Vouchers must be issued by this date. Any requested but not validated and issued by then will be cancelled.
- 31 March 2028. Last date for claims, and the end of the scheme.
The first and last dates are on GOV.UK. The middle one comes from a ministerial written answer of 23 February 2026, which also notes that the dates can change under the scheme's terms (written answer).
If you are in an existing project. Your supplier should have told you. Three things to do:
- Ask the supplier for the project's status and build date in writing.
- Check whether your own voucher has been issued. If you pledged but have not validated it, do that now. After 31 March 2027 it will be cancelled.
- When the service goes live, order it and confirm the connection when asked. The voucher is paid to the supplier only once you are connected, and you may be held to the terms you agreed when you pledged (Openreach).
If you are not in a project. You cannot start one. Some councils added their own money on top of vouchers; the Commons Library cites a £2 million top-up from Northumberland County Council in September 2025 (House of Commons Library). Ask your council whether it runs any local scheme of its own, but expect most top-ups to be tied to voucher projects that already exist.
For what a village can still do without vouchers, see Community broadband: how a village can get full fibre built.
What is the broadband Universal Service Obligation, and how do I use it?
The USO (Universal Service Obligation) was launched in March 2020 (GOV.UK consultation, 2023). It gives every home and business in the UK a legal right to request a "decent" broadband connection: at least 10 Mbps download and 1 Mbps upload. BT must deal with requests everywhere except the Hull area, where it is KCOM (Ofcom, BT).
Do I qualify?
You can make a request if all of these are true (BT, House of Commons Library):
- The address is a home or business at a fixed location.
- You cannot already get a service of at least 10 Mbps download and 1 Mbps upload. Other technologies count, including 4G and satellite.
- Or you can, but only at a price above the affordability threshold. Ofcom's Spring 2026 update uses £59.60 a month (Ofcom). Some documents, including the Commons Library briefing of July 2026, still quote the earlier figure of £54.
- Your address is not due to be covered by a publicly funded build within the next 12 months.
You may be asked for evidence such as a council tax or business rates bill.
The satellite effect
This is the part that catches people out. Because satellite counts, the arrival of cheaper Starlink plans removed many addresses from eligibility. Ofcom's figures for January 2026 show 39,000 premises unable to get decent broadband from a line or a fixed wireless network, but only about 4,000 without an affordable decent service once lower-priced satellite is counted. Ofcom also estimates about 7,000 further commercial premises could be eligible if they cannot get decent broadband for under £59.60 a month (Ofcom).
What decides it is the price of the plan Starlink actually offers at your address. Its cheaper plans are sold only in some areas. If the only plan offered to you costs £80 a month, you are over the threshold. Take a screenshot of the plans and prices shown for your address before you ring BT. How those plans work is explained in the satellite guide.
How to apply, step by step
- Check your address with the postcode checker on BT's universal service page (BT). It first tells you whether a suitable service already exists.
- Ring the universal service help desk on 0800 783 0223 and make a formal request. Note the date and the name of the person you spoke to.
- Wait for the eligibility decision. BT confirms whether you qualify and whether the estimated build cost is under the threshold. This can take up to 30 days.
- If the cost is £3,400 or less (excluding VAT), BT pays and planning starts.
- If the cost is more than £3,400, BT carries out a full survey and sends a detailed quote for the excess. This can take up to 60 days. You then choose whether to pay.
- If you accept, work begins once payment is received. You have 30 days to change your mind; after that the payment is generally not refundable.
- Build. BT says ideally within 12 months, up to 24 months for some builds, and longer in exceptional cases. You should be told the expected timescale early on.
If the quote is over the cap
Quotes above £3,400 are common in remote places and can be very large. Before deciding:
- Ask how the cost has been divided. Ofcom changed the rules in November 2021 on how BT must work out quotes (Ofcom). Ask BT how many other premises the same build would serve and how the excess has been shared between them.
- Talk to neighbours. If several of you would benefit, each making a request strengthens the case and spreads the cost.
- Compare with the alternatives over five years. A £2,000 contribution for a permanent line can be better value than five years of satellite. A £20,000 quote is not.
If you are refused or it goes wrong
- Complaints about the process go to the same help desk.
- If the complaint is not resolved, you can take it to an independent dispute resolution scheme, free of charge. Since 8 April 2026 you can do that after six weeks, down from eight (Ofcom). BT's page still referred to eight weeks when we checked.
- Keep everything in writing: dates, reference numbers, speed tests, and screenshots of any satellite or mobile prices shown for your address.
Will the USO be improved?
Not yet. The government has said it will review the USO, including the 10 Mbps minimum, "in due course" (House of Commons Library), and its 2026 statement of priorities asks Ofcom to work with it on that review (GOV.UK). No timetable has been published.
What help is there in Scotland?
R100. Reaching 100% is the Scottish Government's programme, worth more than £600 million. Three contracts, for the North, Central and South of Scotland, are being delivered by Openreach and almost all of the build is full fibre. The contracts are delivering around 113,000 connections and build is expected to finish in 2028 (Scottish Government). More than 100,000 connections had been delivered across the programme by June 2026 (Scottish Government).
How to check. Use the Scottish Government's address checker, linked from its R100 pages (Scottish Government). It shows whether you are in an R100 contract, in a commercial plan, or neither.
The Scottish Broadband Voucher Scheme. This offers up to £5,000 towards a permanent connection for homes and businesses below 30 Mbps with no superfast build planned. It closes to new applications on 20 November 2026 (Scottish Government). The scheme is supplier-led, so you cannot apply as an individual; a registered supplier has to submit a costed project. If you are reading this after that date, treat the scheme as closed unless a supplier has already submitted a project that includes you.
Project Gigabit in Scotland. UK-funded contracts with GoFibre and Openreach had reached more than 5,600 premises by September 2026 (GOV.UK).
If none of these covers you. In July 2025 about 10,000 premises in Scotland could not get decent broadband from a line or fixed wireless network (Ofcom). The USO applies in Scotland as elsewhere, and the Scottish Government points to low Earth orbit satellite as the fallback (Scottish Government).
What help is there in Wales?
Project Gigabit in Wales. Openreach contracts are expected to reach about 60,000 premises, with more than 7,000 done by September 2026. Gigabit-capable coverage in Wales was 83% in January 2026 (GOV.UK).
Extending High Speed Broadband. The Welsh Government is spending £70 million, recovered from the earlier Superfast Cymru project, on premises that have no superfast service and no plan for one within three years. It works through a framework of suppliers and a series of contracts for groups of premises. The Welsh Government expected roughly 25,000 to 30,000 premises to be in scope and has said delivery will take several years (Welsh Government, June 2025).
Access Broadband Cymru. This grant helped individual homes and businesses pay for an alternative connection where nothing else was available. Its application window closed on 1 May 2026, to be reviewed after the Senedd election of 7 May. People who applied before then can still use the online service to track and claim (Welsh Government). We found no announcement of a reopening by 13 November 2026, so check the Welsh Government's page before assuming either way.
If none of these covers you. About 6,000 premises in Wales could not get decent broadband from a line or fixed wireless network in July 2025 (Ofcom). The USO applies.
What help is there in Northern Ireland?
Northern Ireland has the best fibre coverage in the UK: 95% gigabit-capable in January 2026 (GOV.UK). That is largely the result of Project Stratum, a £200 million publicly backed build by Fibrus that reached more than 81,000 mainly rural premises (PropertyPal news, quoting the Department).
Project Gigabit Northern Ireland. A £34.6 million contract, funded by the UK Government and managed by the Department for the Economy, began in December 2025. Fibrus is due to reach more than 9,000 premises by the end of 2027 (Department for the Economy). The Department has a premises checker showing whether your address is included (Department for the Economy).
If you are not included. Around 1,800 premises in Northern Ireland could not get decent broadband from a line or fixed wireless network in July 2025 (Ofcom). The USO applies, with BT as the provider.
Does my council offer anything?
Sometimes, and it is worth one email to find out. Councils do not usually fund individual connections, but many have a digital or broadband officer who knows which contractor holds the funded contract for your area, what its timetable is, whether the council runs a top-up or community fund, and who else nearby has asked. Councils and operators respond to groups.
What are my rights if my current broadband is slow or keeps failing?
These apply whatever technology you are on, though some depend on your provider having signed up.
Automatic compensation. Providers in Ofcom's scheme must pay without being asked. From 1 April 2026 the amounts are (Ofcom):
| Problem | Compensation |
|---|---|
| Total loss of service not fixed after two full working days | £10.34 a day |
| Engineer misses an appointment, or cancels at short notice | £32.31 |
| New service does not start on the promised date | £6.46 a day |
It covers loss of service, not slow speeds. Not every provider is in the scheme, so check before you choose one.
Complaints and independent resolution. Complain to the provider in writing first. If it is not resolved after six weeks, you can take it to the provider's independent dispute resolution scheme at no cost (Ofcom).
Speed promises. When you signed up you should have been given an estimate of the speed your line can deliver. If you are getting far less, raise it formally. Many providers follow an Ofcom code on broadband speeds that can let you leave without penalty when a line cannot be brought up to the minimum promised. Check Ofcom's website for the current terms and whether your provider has signed.
Landline changes. If your landline is being moved to a digital service and you depend on it, your provider should offer a way to make emergency calls in a power cut, such as a battery backup (GOV.UK).
What if no scheme covers my home?
Then you are choosing between paying for a connection yourself and organising with neighbours.
- Mobile broadband is the cheapest thing to try. Unlimited plans started at about £13 a month in November 2026. See the 4G and 5G guide.
- Satellite works almost anywhere with open sky, from £40 a month at list price. See the satellite guide.
- A community build is slower and harder, and it is the only one of the three that ends with full fibre. See the community broadband guide.
Keep checking the GOV.UK checker every few months, because build plans are reviewed regularly.
What to do next
- Check your address on the GOV.UK gigabit checker, and on the Scottish or Northern Irish checker if you live there.
- If you are in a funded build area, find the contractor and the expected date. Ask the council what it knows.
- If you pledged a voucher, confirm with your supplier that it has been validated and will be issued before 31 March 2027.
- Test your current speed with a cable at a quiet time and in the evening. Keep the results.
- If you are below 10 Mbps download or 1 Mbps upload, look up which Starlink plans are offered at your address and what mobile networks can deliver. Screenshot the prices.
- If nothing affordable reaches 10 Mbps, ring the universal service help desk on 0800 783 0223 and make a formal request.
- If your existing service keeps failing, claim automatic compensation and complain in writing. Go to independent resolution after six weeks.
- If a group of neighbours is in the same position, read the community broadband guide together.
Frequently asked questions
Is the Gigabit Broadband Voucher Scheme still open?
Not for new projects. It closed to new voucher project submissions on 31 August 2026. Projects registered before then continue, and the scheme ends on 31 March 2028.
How much is the broadband USO worth?
BT must pay up to £3,400, excluding VAT, towards the cost of building your connection. If the cost is higher, you are quoted for the difference and can choose whether to pay it.
Can I be refused a USO connection because Starlink is available?
Yes, if a satellite or mobile service offering at least 10 Mbps download and 1 Mbps upload is available at your address for no more than the affordability threshold, which Ofcom's Spring 2026 update puts at £59.60 a month.
How long does a USO connection take?
Up to 30 days for the eligibility decision, up to 60 more days for a detailed quote if the cost is over the cap, then ideally within 12 months for the build and up to 24 months in some cases.
Is there a grant for Starlink or 4G equipment?
Not at UK level. The Welsh grant that could cover alternative connections is closed to new applications, and the Scottish voucher scheme closes on 20 November 2026. Check whether your council has a local scheme.
How do I find out if Project Gigabit covers my house?
Enter your address in the GOV.UK gigabit availability checker. It shows whether gigabit-capable broadband is available, planned or not in any known plans, and whether you are in a funded contract area.
What counts as "decent broadband"?
At least 10 Mbps download and 1 Mbps upload. That is the legal minimum for the USO, not a description of a good connection in 2026.
Can a business use these schemes?
Yes. The USO covers business premises, and funded builds serve homes and businesses alike. Ofcom notes that the cheapest satellite plans are sold as residential, so some business premises remain eligible for the USO where homes are not.
Sources
All sources accessed 13 November 2026.
- GOV.UK, Gigabit Broadband Voucher Scheme information
- GOV.UK, Project Gigabit progress update: September 2026
- GOV.UK, Check your gigabit broadband availability
- GOV.UK, Statement of Strategic Priorities for telecommunications, the management of radio spectrum, and postal services (2026)
- GOV.UK, UK transition from analogue to digital landlines
- GOV.UK, Consultation on reviewing the broadband Universal Service Obligation (October 2023)
- Written parliamentary answer on voucher scheme deadlines (23 February 2026), as reproduced by Parallel Parliament
- Ofcom, Connected Nations update: Spring 2026 (data as of January 2026)
- Ofcom, Nations report 2025 (data as of July 2025)
- Ofcom, How we're changing the rules for the broadband universal service (11 November 2021)
- Ofcom, Quicker complaints resolution and more money in your pocket when things go wrong (8 April 2026)
- BT, Broadband universal service
- House of Commons Library, Getting better broadband (21 July 2026)
- Openreach, Fibre Community Partnership
- Scottish Government, About R100
- Scottish Government, 100,000 connections bring faster broadband (June 2026)
- Scottish Government, Scottish Broadband Voucher Scheme
- Welsh Government, Access Broadband Cymru application notice (1 May 2026)
- Welsh Government, Written statement: Extending High Speed Broadband project (9 June 2025)
- Department for the Economy (Northern Ireland), Broadband and Mobile in Northern Ireland fact sheet (July 2026)
- Department for the Economy (Northern Ireland), Fast broadband to reach over 9,000 rural premises (16 December 2025)
- PropertyPal (news report quoting the Department for the Economy on Project Stratum)
- ISPreview (trade press), April 2026 contract progress for Project Gigabit
- ISPreview (trade press), Norfolk County Council update after CityFibre scale back (September 2026)